The 189 metre long Lang Ha - Thai Ha overpass, running towards Thai Ha street, is built at a total cost of VND 67 billion (US$3.2 million).
The Chua Boc – Tay Son flyover, running along Tay Son street, is 249 metres long and has a total investment of VND 65.5 billion (US$3.1 million).
Both overpasses will be 4.75 metres high, 9 metres wide and consist of two lanes for motorbikes and two lanes for automobiles with a maximum weight capacity of three tonnes.
The two constructions are being built to help ease traffic jams in the southwestern part of the capital and are scheduled to be completed within 180 days.